East Plumbing Co.
Case Study: Hot Water Ring Main Replacement for a Multi-Level Building
Overview
East Plumbing Co. was engaged to replace a failing hot water ring main system within a multi-level building. The existing Aquatherm pipework had developed multiple splits and bursts, resulting in active leaks and ongoing reliability concerns.
The objective of the project was to deliver a long-term, durable solution while minimising water shutdown time and disruption to building occupants.
The Challenge
An initial site inspection and review of hydraulic as-built drawings identified widespread issues with the existing Aquatherm hot water pipework. Multiple failures were present, including active leaks on lower levels of the building.
Key challenges included:
Ageing Aquatherm pipework prone to repeated failure
Active leaks impacting building operations
A complex ring main system spanning multiple levels
The need to minimise hot water downtime during replacement
A coordinated approach was required to ensure the system could be upgraded efficiently and safely.
The Solution
The project was delivered as a single, coordinated upgrade, replacing the remaining Aquatherm pipework with a new 316 stainless steel hot water ring main designed for long-term performance.
Works included:
Project management, SWMS, and insurances
Supply and installation of 316 stainless steel pipework and press fittings
Construction of a new ring main extending throughout the building and up to the roof-level hot water supply bank
Cutting and forming ceiling and plaster penetrations to route new pipework
Scanning and core drilling new penetrations within water meter cupboards
Fire-rated sealing of all new penetrations
Sealing and capping of redundant penetrations following removal of existing pipework
Connection of the new ring main to existing water meter manifolds
Installation of pipe clips, supports, and hangers
Installation of 25mm hot water–compliant lagging
Application of solar heat–compliant lagging to roof-level pipework
Installation of isolation and air bleed valves on flow and return lines
Rectification of existing leaks during shutdown
Servicing of the hot water plant area
Removal of all waste materials from site
To minimise disruption, the final cutover was completed with a single planned water shutdown day, supported by a dedicated on-site team.
The Outcome
The completed works delivered a robust stainless steel hot water ring main, eliminating the recurring failures associated with the previous Aquatherm system.
Outcomes included:
Improved system reliability and durability
Reduced risk of future leaks and unplanned outages
Minimal disruption to occupants during the upgrade
A compliant, maintainable hot water system designed for long-term use
Why This Matters
Hot water ring main failures can result in repeated shutdowns, property damage, and increased maintenance costs. Upgrading to stainless steel pipework provides a long-term solution that supports operational reliability and reduces lifecycle costs.
This project demonstrates East Plumbing Co.’s capability to manage complex, multi-level plumbing upgrades with careful planning, safety compliance, and minimal disruption.
